User Guide
Portfolio Settings
Portfolio Settings control how the portfolio module displays time, maps Jira date fields to the Gantt chart, and calculates working capacity.
Accessing Portfolio Settings
Option 1 - Per Portfolio: Open a portfolio → click the Settings (gear) icon → Portfolio Settings tab
Option 2 - Global: Global sidebar → Settings → Portfolio tab
Settings Reference
| Setting | Description | Example |
|---|---|---|
| Time Display Unit | How hours appear in portfolio table columns | Hours, Days, Story Points |
| Bookings Start Date | Which Jira field maps to the Gantt bar start | "Start date", "Custom field: Planned Start" |
| Bookings End Date | Which Jira field maps to the Gantt bar end | "Due date", "Custom field: Planned End" |
| Hours Per Day | Converts day estimates to hours for capacity | 8 |
| Working Days | Which days count as working days | Mon–Fri |
| Calendar | Working calendar used for Gantt scheduling | Default Jira calendar |
Gantt Chart Date Field Mapping
The Gantt chart requires explicit date field mappings:
- Go to Portfolio Settings → Bookings Start Date → select the Jira field that represents the planned start
- Set Bookings End Date → select the Jira field that represents the planned end
- Click Save
If these are not set, the Gantt chart will not render bars for issues that lack the expected date fields.
Common Field Mappings
| Mapping | Recommended Jira Field |
|---|---|
| Start Date | "Start date" (native Jira field) or a custom Date field |
| End Date | "Due date" (native Jira field) or a custom Date field |
Troubleshooting Gantt Issues
| Problem | Fix |
|---|---|
| Gantt bars not rendering | Verify Start and End date fields are mapped and issues have values in those fields |
| Wrong timeline dates | Check field mapping - a mismatched field (e.g., Created vs Start date) produces wrong bars |
| Bars rendering in wrong position | Confirm Hours Per Day and Working Days match your team's schedule |
Tips
- Configure Portfolio Settings before creating your first Gantt-based portfolio - fixing date mappings after bars are created can cause visual shifts
- Use the same date field mappings as your organisation's existing project management process